Dubbed the “Terminal Area Improvement Program” the design-build project included the complete transformation of Mineta San Jose International Airport including new and renovated terminal buildings, a convenient one-of-a-kind consolidated rental car facility, a simplified roadway system with convenient bypasses to alleviate congestion, state-of-the-art security checkpoints and baggage systems, and sustainable features including a 3.3-acre, 1-megawatt solar farm. With the concurrent management of multiple project elements valued between $20 million and $231 million, management excellence was evident throughout the four year duration of design and construction. Major program elements included:

 

• $97 million Modifications to existing Terminal A
• $105 million New Terminal B
• $42 million Baggage Systems in Terminals A and B
• $22 million Modifications and Demolition of Terminal C
• $230 million Consolidated Rental Car Facility
• $125 million Roadway Improvements
• $19 million completion of the North Concourse

Quick Facts

  • Location San Jose, CA
  • Client San Jose International Airport
  • Industry Aviation
  • Line of Business Construction
  • Completion Date June 2010
  • Duration 36 Months
  • Contract Value $ 667,202,000
  • Sustainability Silver
  • Square Footage 2,656,300 SF

Related Projects

Contact Us

X

Oh no... this website is not a fan of Internet Explorer!

Due to some geeky technical reasons, the Hensel Phelps website is best viewed on any browser other than Internet Explorer. However, if you are a diehard IE fan you can continue to use it, but may have a less than great experience and will receive this annoying reminder every day. We recommend one of the following browsers to take full advantage of the Hensel Phelps website. Thank you!

Chrome   Firefox   Edge